Beginning April 25, 2022, the Eastern District Road & Bridge Department will be starting our reclaiming process. Currently our budget allows us to chip seal approximately 40 of our 120 miles of chip seal roads putting them on a 3-year rotation. The last couple of years we’ve started reclaiming roughly 20 miles of the 40 planned chip seal miles. This process consists of using a reclaimer to dig 6”-7” down into the road, bring the material up, grinding it, then lay it back down. We then water and compact it in creating a smooth & solid sub surface, however this is not the final stage. After letting it set a couple of months for further compaction we will apply another layer of oil and haydite. Below is a list of roads we will be reclaiming with approximate dates the work will be done. These dates are subject to change due to weather and/or equipment issues.
We apologize for any inconvenience this may cause. We are confident this process will improve the quality of our roads while extending their life expectancy.
Road Name Rd.# Est. Length Dates
Woodbine #26 .9 4-25 thru 4-29
Old Frame #321 .9 4-25 thru 4-29
Old Frame #329 1.7 4-25 thru 4-29
SE 95th #122 3.2 4-25 thru 4-29
Hillyard #130 2.6 5-2 thru 5-6
Wilson #131 .5 5-2 thru 5-6
O'Brian #127 .9 5-2 thru 5-6
SE 110th #127 .3 5-2 thru 5-6
SE 110th #129 1.3 5-10 thru 5-13
Crouse #128 1.0 5-10 thru 5-13
Bigham #136 .3 5-10 thru 5-13
Pickett #49 .6 5-10 thru 5-13
Atha #147 .1 5-10 thru 5-13
SE 50th #146 1.0 5-10 thru 5-13
Kelsey #145 .8 5-16 thru 5-20
SE 52nd #145 .5 5-16 thru 5-20
Prescher #152 .8 5-16 thru 5-20
SE 72nd #151 1.1 5-16 thru 5-20
Monroe #151 .9 5-16 thru 5-20