We previously shared in April that our current budget allows us to chip seal approximately 40 miles each year. This represents roughly 1/3 of our total chip seal roads in the Eastern District. During the month of May we reclaimed 22 miles of the 40 miles that are on this year’s list. June 14th, we began our chip seal process on the reclaimed roads. This is scheduled to be completed by July 8th. These dates are subject to change due to weather and/or equipment issues. The remaining 20 miles will be resurfaced beginning August 8th, we will post those roads the beginning of August. See the list below of dates and roads recently reclaimed and ready for chip seal.
June 14 through June 16
Monroe #151
SE 72nd #151
Prescher #152
June 21 through June 24
Old Frame #321
Old Frame #324
SE 95th #122
June 27 through June 30
Bigham #136
Expo
Pickett #49
Atha #147
SE 50th #146
Kelsey #145
SE 52nd #145
July 5 through July 8
SE 110th #127
O’Brian #127
SE 110th #129
Crouse #128
Wilson #131
Hillyard #130